Brynteg, Ynys Mon
Storws WEn
REsidential DEvelopment Site
June 2020
​
With the completion of 2 units and a show home fit out, the properties are now up for sale. This was an important milestone for us as it allows the client to see the fruition of their investement.
​
Click on the following link to view a 3D tour from within once of the properties.
​
​
February 2020
Project milestone as the last of the foundations are completed.
14 of the 20 units are assembled on site and project running ahead of programme.
All efforts now on the 2 units that will be used as show homes. With bookings quickly filling up for the show home event in early April its all go on the site, regardless of the awful weather we have been experiencing as of late.
November 2019
Work started on site early Autumn 2019 and by the end of the first week in November we are erecting the first of 20 timber frame build homes.
Getting to this point required extensive groundworks and site preparation with over 10,000 m3 of topsoil excavated and stored in the adjoining field for later use.
We are programmed to have 5 frames erected by the end of 2019 with roofing and external masonry scheduled to start in January.
​
We are proud to engage and employ local supply chain contractors for this project, with North Wales Timber Frame Limited supplying the timber frames , JR Scaffolding all access and OBR direct employees on the groundworks.